We provided power, lighting, emergency and standby power generation, access control systems, CCTV, and a VESDA fire alarm system for this major data center. The project, engineered by out-of-state consultants, required superplot drawing coordination with the mechanical subcontractor to ensure a seamless installation. It also involved six megawatts of 2 N+1 redundancy power and 13,800 volt paralleling switchgear and generators. Cochran has remained in the facility since its construction, providing maintenance, moves, adds, changes, and upgrades.

  • Electrical, security
  • 100,000 square feet
  • Contract: $80,000,000
  • Lynnwood, Washington
  • Completed 2001

Contractors:
Best Tech Inc.
Evergreen Technologies
Address:
2510 Western Ave
Suite 500
Seattle, WA 98121